| LivingDay |
Date |
Item |
Who |
Notes |
||
| 1 |
Empty kitchen of everything |
Allan & Graham |
||||
| 2 |
Rip out |
contractor |
||||
|
Confirm kitchen cab dates |
Allan |
|||||
| 3 |
Continue rip-out, remove baseboards, and floors |
contractor |
||||
|
Delivery of sink, lights, instant hot tap |
Electrical & plumbing store |
|||||
|
Arrange Appliances delivery dates |
Allan |
Wednesday August 25; 1pm-5pm |
||||
| 4 |
Run electrical wires. |
contractor |
||||
| 5 |
gyp-rock ceiling, first coat of plaster, run speaker wires and ethernet, more electrical wire clean-up |
contractor |
||||
| 6 |
Sat, August 21 |
Must pick up overhead rangetop fan and speak to granite fabricator |
Allan |
|||
| 7 |
Sun, August 22 |
weekend |
||||
| 8 |
Mon, August 23 |
More wiring |
contractor |
No real visable changes |
||
| 9 |
Wiring plumbing |
contractor |
||||
| 10 |
Cabinet delivery and install |
Cabinet company |
||||
| 11 |
Cabinet install |
Cabinet company |
||||
| Confirm date for Granite pre-measure | Allan | |||||
| 12 |
Fri, August 27 |
Nothing scheduled. |
||||
| Arrange delivery of floor | Allan | |||||
| 13 |
Sat, August 28 |
|||||
| 14 |
Sun, August 29 |
|||||
| 15 |
Mon, August 30 |
Wall oven and Microwave installed. |
contractor |
|||
| Plaster ceiling, sand floor | contractor | |||||
| Move A/C duct in kitchen and rebox duct in guest room | Allan | |||||
| 16 |
Sand ceiling |
contractor |
||||
| Exhaust hood installed. | contractor | |||||
| More wall outlets installed | contractor | |||||
| Granite measured and ORDERED | Allan and Prestige Granite | |||||
| Floor delivered | Electrical and Plumbing Store | |||||
| 17 |
Wed, September 1 |
More sanding, priming |
contractor |
|||
| Duct work through office | contractor | |||||
| Lighting check | contractor | |||||
| Sand and plaster duct in guest room | Allan | |||||
| 18 |
Thur, September 2 |
paint ceiling |
contractor |
|||
| Pot light install, switch & plug install | contractor | |||||
| 19 |
Laminate floor install |
|||||
| 20 |
Sat, September 4 |
|||||
| 21 |
Sun, September 5 |
|||||
| 22 |
Mon, September 6 |
Labour Day |
||||
| 23 |
Tue, September 7 |
Gas install |
Ottawa Valley |
|||
| 24 |
Wed, September 8 |
Work on floor | contractor | |||
| Install lights | contractor | |||||
| 25 |
Finish floor |
contractor |
||||
| 26 |
Deslaurier door install |
Cabinet company |
||||
| Run Hood fan duct to garage | contractor | |||||
| 27 |
Sat, September 11 |
|||||
| 28 |
Sun, September 12 |
|||||
| 29 |
Mon, September 13 |
|||||
| 30 |
Tue, September 14 |
|||||
| 31 | Wed, September 15 | Granite Installed | Prestige Granite | |||
| 32 | Thurs, September 16 | mouldings and trim installed, Sink hookup and instant hot install | contractor | |||
| 1/4" plywood backsplash installed for stainless steel | contractor | |||||
| 33 | Fri, September 17 | Dishwasher installed, backsplash 1/4" plywood install | contractor | |||
| Ceiling fans install, Back splash installed | contractor | |||||
| 34 | Sat, September 18 | |||||
| 35 | Sun, September 19 | |||||
| 36 | Mon, September 20 | |||||
| 37 | Tue, September 21 | Met with Manager and Vice President of Cabinet company in my kitchen to go over my concerns about project being so late. | ||||
| 38 |
Wed, September 22 |
Upper cabinets raised 1/2" because they were installed too low for vity bylaw in relation to gas stovetop. | ||||
| 39 | Thurs, September 23 | |||||
| 40 | Fri, September 24 | |||||
| 41 | Sat, September 25 | Drawer faces and handles installed | Cabinet company | |||
| 42 | Sun, September 26 | |||||
| 43 | Mon, September 27 | All drawers slides fixed. Rest of handles and doors installed. Replacement wall oven side panel installed. | Cabinet company | Undercab valence not correct size, corner cab glass shelves still missing | ||
| Lazy susans, drawers, handles, Garage and toekick installed, | Cabinet company | 1 lazy susan still missing, window sill still missing, etc. | ||||
| 44 | Tue, September 28 | Backsplash 1/4" plywood installed, Instant hot hooked up, wall plugs and switches finished. Floor molding patched. | contractor | |||
| 45 | Wed, September 29 | Duct work finished, electrical problem in garage fixed | contractor | |||
| 46 | Thurs, September 30 | Stainless Steel backsplash pre-measure | Stainless steel company | |||
| 47 | Fri, October 1 | Drawer replacements, window sill delivery and cut, undercab light valence delivery and install | Cabinet company | They are now basically finished everything. !!!!! | ||
| Major kitchen cleaning | Mayra | |||||
| 48 | Sat, October 2 | |||||
| 49 | Sun, October 3 | |||||
| 50 | Mon, October 4 | Move back into Kitchen | Graham and Allan | YEAH!!!!! | ||
| 51 | Tue, October 5 | Kitchen light fuse split into 2 due to fuse blow because of Instant Hot tap | ||||
| 52 | Wed, October 6 | |||||
| 53 | Thur, October 7 | Stainless Steel backsplash Install | Stainless steel company | |||
| 54 | Fri, October 8 | Window sill and frame install | contractor | |||
| 55 | Sat, October 9 | |||||
| 56 | Sun, October 10 | |||||
| 57 | Mon, October 11 | |||||
| 58 | Tue, October 12 | Stainless steel toe kick finish and a couple of elect outlet cover changes. | ||||
| 59 | Wed, October 13 | |||||
| 60 | Thu, October 14 | |||||
| 61 | Fri, October 15 | |||||
| October 25, 2004 | FInish walls in eating area and painting | Dave from Details Painting | ||||